March 1, 2022
To all our valued Wayne Dalton Dealers,
I want to provide you with the latest update on lead times. Our objective is to provide you with as accurate information as possible on production lead times from our various manufacturing plants throughout the United States.
The market remains strong and incoming orders continue at historic levels as New Construction continues to be bolstered by items such as a robust economy, strong new development, and low interest rates.
The overall health of the supply chain is still very challenged and several of our suppliers are unable to consistently provide the raw materials we need to meet the increased demand, and this has resulted in additional production delays. Our operations team is working day and night to overcome these challenges and utilize alternatives to create solutions to the evolving conditions.
Please see the new Lead Time update charts below. For more information, please contact your Customer Care Manager.
Sincerely, Pat Duffy
Vice President/General Manager Wayne Dalton
Wayne Dalton – Mt. Hope Plant |
|
Product | Lead Time |
Residential Models * 9100/5120/9605 | 30 weeks |
Residential Models * 8300/8500 | 22 weeks |
Residential Models 6600 | 35 weeks |
Residential Aluminum Models 8450/8850/523RX | 30 weeks |
Residential Models * 9405/9510 | 26 weeks |
9700/9800 Models** | 35 weeks |
Residential Models # 8000/8100/8200/8024/8124 | 12 weeks |
Residential Vinyl Model 8700 | 16 weeks |
Commercial Sectional Steel *** 2411/2415 | 14 weeks |
Commercial Sectional Steel *** Thermospan 150/200 | 20 weeks |
Commercial Sectional Steel *** Thermospan 125 | 30 weeks and/or convert orders to TS 150 |
Commercial Sectional Steel *** ThermoMark 530 (3”) | 26 weeks |
Wood | 30 weeks |
AFV | 30 weeks |
**Model 9700 finish selection excludes TruChoice Custom Color finishes through the remainder of 2021.
*** Commercial section doors with aluminum sash sections will experience additional lead times due to aluminum availability.
#Insulated pan doors add 4 to 6 weeks to the 8000 lead time to allow for build in Pensacola
Wayne Dalton – Pensacola Plant |
|
Product | Lead Time |
Residential Models * 9100/5120 (excluding 23.8” pans, Sonoma Ranch, Desert Tan & Gray) |
30 weeks |
Residential Models * 8000 / 8100 / 8200 / 8024 / 8124 |
15 weeks |
Residential Model * 9405 (white only) | 16 weeks |
Commercial Sectional Steel*** C-2400 / C-24 / C-20 | 2 weeks (QTY < 9) 30 weeks (QTY > 9) |
All other models from Mt. Hope |
MH lead time + 10 days transit |
*Glass will add 2 to 4 weeks. Colors add 2 to 4 weeks
*** Commercial section doors with aluminum sash sections will experience additional lead times due to aluminum availability.
Wayne Dalton – Portland Plant |
|
Product | Lead Time |
Residential Models * 8000 | 12 weeks |
Aluminum Full-View Models 8800/K-AL | 16 weeks |
Commercial Sectional Steel C-24/C-2400*** | 6 weeks |
Commercial Sectional Steel C-20*** | 6 weeks |
All other models from Mt. Hope |
MH lead time + 10 days transit |
Wood**** |
6 Weeks |
*Glass will add 2 to 4 weeks. Colors add 2 to 4 weeks
*** Commercial section doors with aluminum sash sections will experience additional lead times due to aluminum availability.
**** Certain species of wood and specialty could have longer lead times
Wayne Dalton – Dalton Plant |
|
Product | Lead Time |
800 (3” Service Doors) and 900 (2” Service Doors) | 26 weeks |
Counter Shutter and Fire Shutter doors |
26 weeks |
Fire Doors Models 702 and 704 |
26 weeks |
3” Insulated Service Doors And Insulated Fire Doors | 26 weeks |
600 Rolling Grilles |
26 weeks |
Powder Coat Doors |
26 weeks |